Hampton Bays Water District

Posted on: January 28, 2021

[ARCHIVED] COMPLIANCE SCHEDULE FOR DEFFERAL

Hampton Bays Water District Logo

COMPLIANCE SCHEDULE FOR DEFFERAL

 Begin Enhanced Monitoring Period:           November 2020

Complete Engineering Report:                    April 2021

Complete Design and Submit to DOH:       August 2021

Commence Construction:                             October 2021

50% Completion:                                         March 2022

Complete Construction:                               June 2022