COMPLIANCE SCHEDULE FOR DEFFERAL
Begin Enhanced Monitoring Period: November 2020
Complete Engineering Report: April 2021
Complete Design and Submit to DOH: August 2021
Commence Construction: October 2021
50% Completion: March 2022
Complete Construction: June 2022